FHWA
Hot Mix Asphalt Pavement Guidelines
Project Information:
Project Description:
Contract No:
Series (50, 60, 70,
80):
Nominal Layer Thickness
(mm):
Item Number:
PIN:
In company with:
Date of Inspection:
Inspection Made By:
Time of Day:
Contractor:
Time Elapsed
(%):
Work completed
(%):
This guideline was prepared utilizing the below references. The
checks included in the guidelines are considered to be the major
items and can be supplemented as deemed necessary by the
inspecting party. The Area Engineer is provided the flexibility of
using the guideline in its entirety or portions depending on the job
conditions and/or time limitations.
NOTE: The vast majority of paving done on __DOT projects today
utilize performance related specifications. Under performance
related specifications, the contractor is responsible for compacting
the pavement within a specified density range (Series 50, 60, and
70). Because the contractor is responsible for compacting the
pavement, then the contractor should have the authority to dictate
factors such as mix temperature (165 °C is the maximum), rolling
trains, patterns, or passes.
References:
1. Standard Construction Specifications
2. Current Quality Assurance Program for Hot Mix Asphalt and
Concrete Pavements
3. Applicable Special Provisions
4. Hot-Mix Bituminous Paving Manual, Federal Highway
Administration
5. Hot-Mix Asphalt Paving Handbook, US Army Corps of Engineers
6. Hot Mix Asphalt Construction, Participant Manual for NHI Course
13132
HMA Materials
Materials mixed at any HMA plant must have prior State approval.
Course and fine aggregate sources must be approved by the
Regional Materials Engineer. The Superpave Mix Design must
satisfy the requirements of Section XXX and the mixture design
procedure as written in Materials Method X.X and be submitted to
the Regional Materials Engineer. The State DOT website has a list
of all approved material sources/suppliers.
a. Has the Superpave Mix Design/Job Mix Formula (JMF) been
submitted and approved by the Regional Materials
Engineer? Ask for a copy.
YES NO
Part I : Paving Operation - Field Portion
Pre-paving Meeting- Prior to the start of the paving operation, a
pre-paving meeting should be held approximately one week before
paving operations commence and key personnel (placement,
inspection and supply). The contractor should present the paving
'plan' discussing surface preparation, paving and compaction
widths/sequences, temperatures, compaction, equipment pre-check
arrangements, etc. Such meetings shall be documented in the
Engineer's Diary. Was a pre-paving meeting held? YES NO
I. Weather and Seasonal Limitations (specification
reference)
Do not place HMA plant mix on any wet surface or when the
surface temperature is less than specified in Table XXX,
Temperature and Seasonal Requirements, or when weather
conditions will prevent proper handling or finishing of the
HMA mixtures.
a. Is the minimum surface temperature being observed based
on the course thickness in Table XXX(applies to all surface
course paving whether it is on the mainline or shoulders)?
YES NO
TABLE 402-2
TEMPERATURE AND SEASONAL REQUIREMENTS
Nominal Compacted Lift
Thickness
Surface Temperature Minimum
(Note 1)
Seasonal
Limits
>=100 mm
5 °C (40 °F)
None
>= 50 mm but < 100 mm
8 °C (47 °F)
Notes 2 & 3)
< 50 mm
10 °C (50 °F)
(Notes 2 & 3)
2. Measure all temperatures on the surface where the mixture
is to be placed and the controlling temperature will be the
average three temperature readings taken at locations ±8
meters apart.
3. Place Top Course only during the period of April 1stup to
and including the third Saturday of November in the
counties of ...
4. Place Top Course only during the period of May 1st up to
and including the third Saturday of October in all counties
except as noted in Note 2
(Above table provides lift thickness and applicable
temperature criteria)
An approved warranty is the only mechanism, which allows
the contractor to place top course HMA outside the
weather, seasonal and temperature requirements of the
specifications.
II. Construction Equipment
HMA Pavers (Spec reference)
HMA Paver Manufacturer: Model Number:
. Is the HMA Paver self-powered? YES NO
a. Is it capable of lane width placement? YES NO
b. Is the screed heated at the beginning of the paving
operation or after periods of extended shutdown to
avoid sticking? YES NO
c. Is the automatic transverse slope control approved?
YES NO
d. Is the automatic longitudinal grade screed control
approved? YES NO
e. From what references do the controls operate (fixed
or moving)? Controls must be approved by the EIC.
______ FIXED (taut reference line at or near
pavement centerline or edge supported at approx. 8m
intervals)
______ MOVING (floating beam, ski, or other suitable
type at least 9m in length)
f. Are auger and tunnel extensions mounted on the
paver when the screed is extended more than 0.3 m
for fixed paving widths wider than 3.6m?
YES NO NA
g. If the paving width is greater than 5.2 m, are the
references on both sides of the pavement?
YES NO NA
h. Was the paver examined and approved? Items to be
examined include the screed (for warping), vibrators,
heaters, grade control mechanism, etc. YES NO
Hauling Equipment (Section 402-3.03)
i. Is the truck bed clean and free of foreign debris (dirt,
gravel, etc.)? YES NO
j. Is the HMA covered with waterproof cover during
transportation? YES NO
k. When hauling beds are lubricated, are approved
release agents being used? YES NO
Release
Agent:_____________________________________
Rollers (Spec reference)
Roller:
Type:
Manufacturer:
Model #:
1 - Breakdown
2 - Intermediate
3 - Finish
Are the rollers examined and approved? YES NO
L. Vibratory Roller
a. Is the vibratory roller model on the State's
current Approved List for Hot Mix Asphalt
Vibratory Compaction Equipment?
YES NO NA
b. Vibratory Rollers shall met the following
requirements when not on the 'approved list':
Nominal Amplitude
1.25 mm maximum
Vibration Frequency
1500 vpm minimum
Drum Width
(dual vibrating drums)
1.3 m minimum
(single vibrating drum)
2.1 m minimum
c. Does the vibratory roller meet these
requirements? YES NO NA
d. All vibratory rollers shall be equipped with a
speedometer that accurately indicates roller
speed in either 1km/hr or 15 m/min increments
(maximum). Does the roller have an
acceptable speedometer? YES NO NA
e. Does the vibratory roller have a Materials
Bureau approved speed control device, which
prevents speed in excess of 4 km/hr or 67
m/min when the roller is in vibratory mode?
YES NO NA
M. Static Steel-Wheel Roller
The static steel-wheel roller shall be self-propelled
and be either:
a. 9 to 11 metric ton tandem three axle type
b. 7 to 9 metric ton tandem two axle type
Check the rating plate on equipment or equipment
'specification sheet' provided by contractor. Does the
roller meet these requirements? YES NO
N. Pneumatic Rubber-Tire Roller
Pneumatic rubber-tire rollers shall be self-propelled
and consist of two axles on which multiple pneumatic-
tired wheels are mounted in such a manner that the
rear wheels shall not follow in the tracks of the
forward wheels and would be spaced to give
essentially uniform coverage on each pass. An
approved release agent shall be applied to the tire to
prevent picking of material. Pneumatic rollers shall
meet the following requirements unless otherwise
approved:
Maximum Wheel Load
2,600 kg
Tire Compression on Pavement
550 ±35 kPa
Maximum Axle Load
10,160 kg
Does the pneumatic roller meet these requirements?
YES NO NA
III. Conditioning of Existing Surface (Spec reference)
. Is the condition of the subgrade, base, or bituminous
surface satisfactory for HMA placement? (ex. clean,
dry, etc.) YES NO
a. Is the tack or prime coat specified (Spec reference)?
YES NO
b. The tack coat shall be uniformly applied to a prepared
clean surface of all contact surfaces including all
pavement layers, pavement edges, curbing, gutters,
manholes and other structures. The tack coat shall
not be applied to wet pavement surfaces or when the
surface temperature is elow the temperature
requirements in Table XXX. The application rate shall
be approved by the Engineer and be between 0.14 to
0.32 L/m
2
.
What is the tack coat application rate?
_____________
Does the tack coat application meet the above
requirements? YES NO
c. Does the tack coat precede the asphalt paving such
that the tack is not damaged? YES NO
d. Are the depressions and wheel path ruts filled prior to
the paving of the truing and leveling course?
YES NO
IV. Spreading and Finishing (Spec reference)
. Paving over a tack coat should not commence until
the emulsion has broken (goes from brown to black)
or is tacky when touched. Was this requirement met
before paving commenced? YES NO
a. Does the delivery tickets contain the correct
information: the contract number, item number, job
mix formula, tonnage, date, and time? YES NO
b. When placed, what is the temperature of the mix?
________
The temperature should be within 10 °C of the
temperature specified by the contractor.
c. Is the truck delivery of the plant material frequent
enough to prevent idling of the pavement operation
resulting in rollers standing on a fresh mat?
YES NO
d. When trucks are dumping into the hopper, are wheels
in contact with rollers? YES NO
Is any excess bumping observed? YES NO
e. Is the paver running at a constant speed to match the
delivery of asphalt? YES NO
If not, the paver should stop and start smoothly and
quickly.
f. Is a constant head of material kept in front of the
screed and in the hopper? YES NO
Is any excess material dropped in front of the paver?
YES NO
g. Is the paver equipped with automatic grade/slope
controls? YES NO
Normally automatic controls are required unless
existing grades at roadway intersections or a drainage
structure must be met or if paving shoulders,
temporary detours, behind curbs, or in other areas
where its use is impractical as determined by the
Engineer.
h. Are the following being checked and at what frequency?
depth checks observed frequency
________________ YES NO
mat temperature observed
frequency_________________ YES NO
cross slope observed
frequency_________________ YES NO
i. Is the loose mat checked, any irregularities adjusted,
and all unsatisfactory material removed and replaced
prior to the beginning of rolling? YES NO
V. Compaction (Spec reference)
. Is the proper compaction method associated to
specific items being placed being utilized**?
YES NO
____ 50 Series (A) - Performance based target
density (PBTD), requires daily coring
____ 60 Series (B) - PBTD - specifies core samples
and nuclear density gauge
____ 70 Series (C) - PBTD - nuclear gauge with initial
calibration, low volume jobs
____ 80 Series (D) - Method specified dependent on
pavemen course (ranges are 4-6 passes vibratory
and 2-4 passes static)
**Refer to Section XXX for detailed requirements and
options for each compaction method.
a. Is there a specified rolling pattern for this job?
YES NO
If yes, what is it and is it being implemented on site?
YES NO
b. Initially roll all courses with the roller traveling parallel
to the centerline of the pavement beginning at each
edge and working towards the center. Is this method
being followed? YES NO
c. Are the banked curves rolled starting at the low side
edge and working toward the super-elevated edge?
YES NO NA
d. Are the rollers moving at a constant, slow speed with
the drive wheels nearest the paver? YES NO
e. Are the roller wheels being kept moist (use of fuel oil
is prohibited)? YES NO
f. If the roller displaces any material, is the material
replaced and grade restored to original grade?
YES NO NA
g. There shall be no visible defects, such as shallow
ruts, ridges, roller marks, cracking, tearing,
segregation, or any other irregularities in the
pavement when the rolling operation is complete. Are
there any visible defects? YES NO
If yes, what are they?
______________________________________
VI. Joints (Spec reference)
. The pavement of successful courses will be such that
all joints are offset no more than 150mm from the joint
of the lower pavement course, unless approved by
the Engineer. Is this requirement met?
YES NO NA
a. Is the transverse joint compacted in static mode with
the roller parallel to the joint and perpendicular to
traffic? YES NO NA
b. On the top course, is the longitudinal joint on the lane
line? YES NO NA
c. An exposed joint in excess of 30 meters must be a
tapered edge joint. If left overnight, warning signs
must be placed at a maximum spacing of 300 meters
to alert drivers.
VII. Surface Tolerance (Spec reference)
. Construct the pavement surface to a 6mm tolerance.
Has the State determined a need to check the surface
tolerance utilizing a 5 meter straight edge or string
line placed parallel to the centerline of the pavement
and with a 3 meter straight edge or string line placed
transversely to the centerline of the pavement on any
portion of the pavement? YES NO
a. Are any irregularities exceeding the 6mm tolerance
limits corrected? YES NO
VIII. Thickness Tolerance (Spec reference)
A depth tolerance not to exceed 6mm from the nominal
thickness required (per plan) for the course specified under
one pay item will not be acceptable where the required
nominal thickness is 100 mm or less. A tolerance not to
exceed 13 mm from the nominal thickness required for the
course or courses specified under one pay item will be
acceptable where the required nominal thickness is over 100
mm. The total thickness of all HMA mixture courses will not
vary from the total nominal thickness indicated on the plans
by more than 6 mm where the total nominal thickness is 100
mm or less; or by more than 13mm where the total nominal
thickness is over 100mm but not more than 200 mm; and by
not more than 16 mm where the total nominal thickness is
more than 200 mm. When the HMA mixture is placed on
newly constructed subbase material, an additional tolerance
of plus 6 mm will be allowed both in the nominal thickness of
the course placed directly on the subbase and the total
pavement thickness.
. Are depth checks being taken? YES NO
Nominal Thickness (per plan): ____________
Depth Check Readings: (after compaction) _________
_________ _________ ________
IX. Pavement Density Samples (Spec reference) &
Compaction Testing (Spec reference)
Test Section
The contractor will pave a test section for Series 50, 60, and
70 paving.
What is the date and location of placement of the test
section associated with the paving operation?
Date:______________
Location:_________________________
. What were the results?
a. What was the loose-lift and after compaction layer
thickness?
Loose-Lift Thickness _________ After Compaction
Thickness___________
b. Was the test section the same depth, at least 50 m
long and used the same equipment as the paving
operation? YES NO
c. How was the pavement density determined?
______ Coring ______Nuclear Gauge
d. If the nuclear gauge is used, was the density
measured after each roller pass? YES NO
Core Testing
e. Is coring required for this lift? (see proposal)
YES NO
f. Has the project staff randomly defined four 150 mm
diameter Coring locations per lot? YES NO
g. Have these locations been withheld until the
compaction operation is complete? YES NO
h. How did the project staff determine the random
locations?
______Material Bureau computer program "Random"
______Random # table from XX(spec reference)
i. Have the cores been wrapped in a red security seal
immediately after drilling in the presence of a state
inspector? Has form BXXX been completed, put into a
waterproof envelope and placed with the core in a
polyethylene bag? YES NO
j. Has the contractor elected to test the cores under
Materials Procedure (Spec Reference) YES NO
k. Were 4 loose mix samples taken on each paving day
(in accordance with AASHTO T 168-97)? YES NO
l. Check the Quality Adjustment Factors (QAF) for the
placed asphalt pavement. Is the pavement of
adequate quality? YES NO
Nuclear Gauge (if applies)
m. What is the project target density (PTD) from the test
section? ____________________
n. Is a qualified technician conducting the compaction
testing? YES NO
o. Is the required density being obtained prior to the mat
temperature reaching 79 °C? YES NO
p. Are random locations determined at 50m intervals?
YES NO
q. Are any two consecutive readings (four
measurements) <PTD*0.96? YES NO
r. Is the 10 test moving average >PTD*0.98?
YES NO
PART II: PAVING OPERATION - OFFICE PORTION
This section pertains to the review of the office records for the
paving operation. This section can be completed at a follow up visit
once the test results are obtained (typically 7-10 days) for the
paving operation reviewed in Part I or office records for a previous
date of paving for this project can be reviewed.
This review is for:
____ the paving operation reviewed in Part I
____ a previous paving operation dated ________________.
(randomly selected)
Description:____________________________________________
___________________________________________
_____________________________________________________
___________________________________________
Check the inspector's daily reports (IDR,s), pavement delivery
tickets, core results and pay estimate for proper documentation of
materials used, pay items involved, and required field tests and
results (eg. temperatures of base and mix, yield and depth checks,
application rate of prime or tack).
Dates sampled
_____________________________________________________
______________________
IDR's
_____________________________________________________
_____________________________
_____________________________________________________
__________________________________
Pavement delivery tickets
_____________________________________________________
_____________
_____________________________________________________
__________________________________
Pay Estimate
_____________________________________________________
_______________________
_____________________________________________________
__________________________________
Other Comments:
_____________________________________________________
___________________________________
_____________________________________________________
___________________________________
_____________________________________________________
___________________________________
_____________________________________________________
___________________________________
_____________________________________________________
___________________________________
Overall Quality of Project Paving to Date (Describe quality payment
adjustments, deficiencies, etc.):
_____________________________________________________
___________________________________
_____________________________________________________
___________________________________
_____________________________________________________
___________________________________
PART III - CONCLUDING REMARKS
1.a. From your roadway review, do the plans and specifications
appear adequate to obtain the desired product?
_____________________________________________________
___________________________________
_____________________________________________________
___________________________________
_____________________________________________________
__________________________________
b. Based on discussions with the State personnel, are there any
suggestions for changes in the procedures or requirements that
might better improve the process?
_____________________________________________________
__________________________________
_____________________________________________________
__________________________________
_____________________________________________________
__________________________________
2. Hold a closeout conference and discuss all findings and how, if
any, corrective actions will be performed?
_____________________________________________________
__________________________________
_____________________________________________________
__________________________________
_____________________________________________________
__________________________________
_____________________________________________________
__________________________________
_____________________________________________________
__________________________________
_____________________________________________________
__________________________________
3. Summarize findings that are not procedural/project related and
will need to be pursued beyond the individual project. This would
include items related to standard plans, specifications, construction
directives, materials procedures and the like.
_____________________________________________________
__________________________________
_____________________________________________________
__________________________________
_____________________________________________________
__________________________________
_____________________________________________________
__________________________________